OpenAI pledges local compacts for its future data centres and asks US policymakers to make big electricity users pay the grid costs they create
OpenAI says every future compute campus it owns and operates will get a local compact, with pledges to pay the full cost of its power, publish site-level water and electricity use and not use NDAs with public officials. A separate blueprint asks lawmakers to turn similar rules into law.

OpenAI published a "National Community Compact" and a "Compute Campus Policy Blueprint" on Thursday 5 November 2026 (its news feed timestamps the post 02:00 GMT). The company says: "Every future compute campus OpenAI owns and operates will have its own local compact." Everything below is OpenAI's own pledge, proposal or account, not an independently reported outcome.
Our text of OpenAI's announcement comes from a reader render (r.jina.ai) of its page, because openai.com refused our direct request. We read both PDFs directly from OpenAI's CDN.
What OpenAI says it will do
The eight-page compact has eight headed sections. By our count, six of them hold 15 bulleted "We will" commitments; a "Grid Protector" section and a closing "Be a good neighbor" section add pledges in prose. In OpenAI's words:
Listening and accountability
- "We will solicit community input."
- "We will designate a local point of contact."
- "We will not use non-disclosure agreements (NDAs) with public officials." OpenAI adds that it "will allow only narrow protections covering legitimate security information, trade secrets, or proprietary or competitively sensitive information."
- "We will publish construction plans", covering traffic, noise and lighting.
- "We will provide clear public information about community impacts, including noise measures, energy use, water use, and long-term sustainability." This includes commissioning "independent noise studies before operations begin and annually afterward"; new campuses "will publicly report water use by location"; and "We will also publish our on-site electricity use, including electricity generated and consumed." OpenAI also promises site-specific sustainability information and economic-impact reports.
- "We will publicly report progress on the Compact commitments", and the compact says this reporting will be annual.
Energy costs
- "We will protect ratepayers." OpenAI says: "We will pay the full cost of powering our compute campuses and ensure local residents do not foot the bill for our energy needs." It says it "signed the national Ratepayer Protection Pledge".
- "We will provide insurance against stranded assets", meaning financial assurances "if a project is delayed, reduced, or canceled."
- "We will help utilities plan more effectively."
- As a "Grid Protector", OpenAI "will promote and participate in flexible demand programs". It says these "could include" cutting demand at peak times, supplying power back to the grid and smoothing load, "Depending on local conditions, technical feasibility, and utility interest".
Water, local economy and jobs
- "We will develop community-specific water plans", prioritising "closed-loop or low-water cooling systems".
- "We will make sustained investments in community-selected priorities."
- "We will help communities plan for an influx of new tax revenue."
- "We will publish workforce strategies and annual progress reports."
- "We will set local hiring goals where local labor conditions allow it."
- "We will invest in community workforce priorities." Project labour agreements, "AI Talent Hubs" and apprenticeships are listed as options that communities "may consider".
What it asks policymakers to do
The 18-page blueprint says "voluntary measures alone don't meet the scale of this moment". It says its proposals "reflect new commitments we will apply to OpenAI-owned and operated compute campuses moving forward" and adds: "We encourage policymakers to enact them as laws". By our count, it sets out 26 bulleted proposals across five numbered sections. Among them:
- Who pays for the grid: "Policymakers should direct state public utility commissions to create large-load tariffs that require large electricity consumers to pay the incremental costs they create." OpenAI says this "should codify the national Ratepayer Protection Pledge", and that utilities "should secure financial assurances" before major spending begins.
- NDAs: "Policymakers should prohibit data center developers from requiring public officials to sign non-disclosure agreements", with any exception kept narrow.
- Disclosure: required reporting of water use by location, independent noise studies, total facility electricity use and annual power usage effectiveness (PUE), plus site-specific environmental and economic reports.
- Grid connection and supply: voluntary demand-flexibility programmes. OpenAI argues that "Blanket requirements that a large customer build its own power supply can undermine the ability of large customers to subsidize ratepayers". It asks Congress to give the Federal Energy Regulatory Commission "clear authority to establish a faster connection process for ready-to-build projects that advance national economic, security, or critical-infrastructure priorities, subject to reliability and ratepayer protections" and to "expand federal backstop authority" for transmission, and it asks policymakers to "restore and expand technology-neutral clean electricity tax incentives".
- Tax incentives: states and local governments "should publicly disclose discretionary incentive agreements", require measurable performance commitments, and include reporting and clawback provisions if material commitments are not met.
- Jobs: developers should be required to publish workforce strategies and to set local-hiring goals "where local labor market conditions allow".
The blueprint also presents the buildout as part of competition with China, and it says OpenAI "continues to support the strengthening of export controls on chips and semiconductor manufacturing equipment."
Where it applies
The compact covers future campuses that OpenAI owns and operates. The documents name Effingham County, Georgia, Pike County, Ohio, and Abilene, Texas, and mention community projects in Michigan and Wisconsin. OpenAI says it has "committed $80 million to community priorities in Effingham County, Georgia, and $40 million in Pike County, Ohio", and that "In July, we voided NDAs in Effingham". It says its agreement with Georgia Power "allows the utility to reduce the power it delivers to us by up to 1,000 megawatts during periods of high demand." The blueprint quotes Georgia Power as saying customers "are expected to see savings of at least $15 per month beginning in 2029" for a typical residential customer. We have not checked Georgia Power's own release.
What the documents do not say
We read the reader render and every page of both PDFs. They give no date for when the compact takes effect or when the first annual reports will appear, beyond "moving forward" and "future". They do not list which current or planned campuses count as owned and operated by OpenAI, though the blueprint's accountability passage cites Effingham. They set out no independent audit of the compact as a whole (the independent element is the noise studies) and no penalty or enforcement mechanism if OpenAI falls short. Clawbacks appear only in the blueprint's proposal for public tax incentives. No other AI company is named. The partners named are SB Energy and Georgia Power.
Why it matters
On our reading, the compact relies on OpenAI's own annual public reporting for accountability, while the blueprint asks lawmakers to make similar rules binding on all developers. Also on our reading, the first test is whether the promised site-level water and electricity figures appear, because the documents give no date for them.
Ask Relay — he reads every question himself and replies personally by email.