OpenAI's 10-Gigawatt Ohio Ambition: a Reported $500B Campus, Backed by Nvidia
A report says OpenAI is in advanced talks to lease one of the largest data centres ever conceived — on federal land, financed with Nvidia's help. The scale is almost hard to picture.
- 01Per a report from The Information, OpenAI is in advanced talks to lease a proposed 10-gigawatt data-centre campus on federal (Department of Energy) land in southern Ohio.
- 02The campus could cost at least $500 billion to build; OpenAI would control the equipment under a 20-year lease with payments starting at operations, first phase expected ~2028.
- 03It would be developed by SB Energy, a SoftBank unit; Nvidia is expected to supply hardware and provide a financial guarantee for the lease and financing.
- 04Caveat: this is a single-source report (The Information) that Reuters said it could not immediately verify — treat the specifics as reported, not confirmed.
- 05If real, 10GW is an almost unimaginable scale — on the order of ten nuclear reactors' worth of power for a single AI campus.

The numbers in AI infrastructure keep losing touch with intuition. The latest, per a report from The Information: OpenAI is in advanced talks to lease a 10-gigawatt data-centre campus in Ohio.
What's reported
According to the report — widely syndicated via Reuters and others — OpenAI is negotiating a 20-year lease on a proposed campus on Department of Energy land in southern Ohio, developed by SB Energy, a unit of SoftBank. The build could cost at least $500 billion; OpenAI would control the equipment, with lease payments starting once it's operational and a first phase expected around 2028. Nvidia is expected to supply the hardware and provide a financial guarantee for OpenAI's lease and SB Energy's financing.
Put 10 gigawatts in perspective
10GW is not a normal data-centre number. A large data centre today might draw tens to a few hundred megawatts. 10,000 megawatts is on the order of ten nuclear reactors' worth of power dedicated to a single AI campus — which is exactly why federal land, SoftBank-scale development and Nvidia financial guarantees are even in the conversation. This is infrastructure at the scale of national energy planning.
The caveat that matters
This is a single-source report. The original came from The Information, and Reuters said it could not immediately verify it. Neither OpenAI, Nvidia nor SoftBank has confirmed the specifics. So treat the figures as reported, not official — the kind of story that's directionally important even before it's nailed down.
Why it matters either way
True or not-yet-true, the report fits a clear pattern: the frontier labs increasingly believe the binding constraint on AI isn't algorithms — it's power and compute at industrial scale. When the plans on the table are measured in gigawatts and half-trillions, the race has stopped being about models alone and become about who can physically build the most intelligence.
Ask Relay — he reads every question himself and replies personally by email.